'

R-Guard Installation Detail

Rough Opening with FastFlash & Building Wrap

wood construction with plywood/OSB sheathing

Download this detail

R-Guard-Install-4.6-Rough-Opening--FastFlash-and-building-wrap-wood-construction-with-plywood

1.

Apply FastFlash and Joint & Seam Filler as shown here.

 

 

2.

Cut existing building wrap way from rough opening a minimum of 2 inches.

 

3.

Apply AirDam to the outer edge of the rough opening and tool to a minimum of 20 wet mils.

 

4.

Press building wrap into wet AirDam.

 

5.

Apply AirDam at interface of building wrap and rough opening, and tool it to a minimum of 20 mils, so that it half covers the building wrap and half overlaps into the rough opening.

Ted Barnekoff - Air & Water Barriers, PROSOCO

Ted Barnekoff
Product Support - Air & Water Barriers

READY TO HELP

At Prosoco, real humans answer the phone, so why not give them a call?