R-Guard Installation Detail

Rough Opening with FastFlash & Building Wrap

metal studs with gypsum sheathing/OSB sheathing/plywood

Download this detail

R-Guard-Install-4.5-Rough-Opening--FastFlash-and-building-wrap-metal-studs-with-gypsum-sheathing

1.

Apply FastFlash or Joint & Seam Filler as shown here.

 

2.

Cut existing building wrap way from rough opening a minimum of 2 inches.

 

3.

Step Three Apply AirDam to the outer edge of the rough opening and tool to a minimum of 20 wet mils.

 

4.

Press building wrap into wet AirDam.

 

5. Apply AirDam at interface of building wrap and rough opening, and tool it to a minimum of 20 mils, so that it half covers the building wrap and half overlaps into the rough opening.